NYC, i am from rockland county. If you want, pm your contact info, and if i ever get some work out that way i could get it to you. Thats pushing my service area limit.
Demopro, I looked at it but did not bid. I am curious to see what your ball park number came in at. I thought to myself on paper around between 80-100k. Were you in the same area? Pm me your contact info as well!
What is going to happen to the wall that remains? Will it be rebuilt with masonry, EIFS, or will a new building be attached to it?
The last one we did, we stopped our demo one set of columns away from the point of the building that was remaining. We left that row of columns in place and cabled the columns for shearing. A new masonry wall was built to the underside of the existing columns. We then went in and removed that last part of the structure.We had to use some shoring in some areas where some beams were in place over windows.
Keep in mind that this was done with a demising/shoring plan.
If you already own the work, at least get an engineer to take a look.
Oh yeah, we also had to weld some reinforcing steel inside the building that was remaining.
The other thing that is a real big concern will be weather protection.
8:42 AM
April 24, 2007
They are solid poured with concrete sitting on a 6" slab on top of 6" crush and run. I've talked to a few contractors about doing the shoring, but they aren't to thrilled about excepting the liability if the wall collapsing, not only that, but the stores that aren't being torn down are going to be open for business while we tear the 80% of the shopping center down.
Most Users Ever Online: 429
Currently Online:
106 Guest(s)
Currently Browsing this Page:
1 Guest(s)
Member Stats:
Guest Posters: 54
Members: 3039
Moderators: 0
Admins: 2
Forum Stats:
Groups: 4
Forums: 17
Topics: 19952
Posts: 28186
Administrators: JOHN: 7602, John: 6950