Avatar

Please consider registering
guest

sp_LogInOut Log In sp_Registration Register

Register | Lost password?
Advanced Search

— Forum Scope —





 

— Match —





— Forum Options —





Minimum search word length is 3 characters - maximum search word length is 84 characters

sp_TopicIcon
Jamestown Bridge
November 28, 2006
5:18 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The final underwater blast at the old Jamestown Bridge site is set for Wednesday, the state Department of Transportation said.

The DOT said the controlled explosive demolition will remove two underwater piers on the Jamestown side of the bridge. The blast is set for about 9 a.m., barring any delays caused by the weather or safety concerns.

The department said the final detonation will be similar to 10 previous underwater blasts that have been happening since August. Traffic will be cleared from the Jamestown-Verrazzano Bridge during the demolition.

Wednesday's underwater demolition is among the final elements of the $19.5 million project to remove the old Jamestown Bridge. The demolition began with the implosion of the bridge's distinctive center span in April.

Underwater debris clean up will take place through February. In the spring, landscaping and removal of the construction staging areas will take place, the DOT said.

November 1, 2006
6:51 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The next underwater demolition for the old Jamestown Bridge is scheduled for Thursday.

Several piers have already been destroyed in previous underwater demolition efforts.

Thursday's detonation will include one pier segment on the North Kingstown side of the bridge and perhaps a segment on the Jamestown side.

Department of Transportation officials say Thursday's work will mean a minor traffic impact for motorists trying to cross the nearby Jamestown-Verrazzano Bridge. But the bridge will not need to be closed, as was originally planned.

September 28, 2006
6:47 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The next underwater demolition for the old Jamestown Bridge is scheduled for Thursday (Today) at noon, according to the state Department of Transportation. The detonations will be comprised of two pier segments on the North Kingstown side of the bridge.

The detonations will be similar to four underwater demolition events in August and the latest on Sept. 14. Traffic impacts on the Jamestown-Verrazzano Bridge will be kept to a minimum during the demolition.

Just before the detonations, State Police will execute a "rolling block" by moving slowly in all lanes of travel to momentarily clear traffic from the bridge. This approach should avoid the need to conduct a 30-minute closure of the bridge, as was originally planned for the underwater detonations. Between four and five more underwater detonations are planned for the next several weeks.

August 17, 2006
9:47 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The state Department of Transportation says four remaining piers will be detonated on August 23rd. The bridge's center truss was demolished in April. The detonation is one of the last remaining steps in taking down the entire bridge.

Workers in the last several weeks have been breaking apart the concrete piers down to the waterline. The transportation department says the explosives will blow the piers far enough below the surface to pave the way for safe boat navigation.

August 2, 2006
7:15 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The center span is gone and so are the deck trusses and girder spans that once led to it.

Next up for the old Jamestown Bridge demolition project is the removal of the concrete piers.

The first of up to 13 detonations to remove the piers is scheduled for next Tuesday at 10 a.m., the Department of Transportation announced yesterday.

The detonations will remove what's left of more than two dozen piers that once supported the two-lane bridge, taking them down to mud level to allow safe passage of boats and ships, said Frank Corrao, a DOT engineer.

Tuesday's detonation will focus on two piers on the North Kingstown side of the bridge. Other detonations will follow about every other week, Corrao said.

Unlike the major detonations that removed the old bridge's center span and deck trusses in April and May, the upcoming small-scale pier detonations will not require three- to four-hour closures of the adjacent
Jamestown-Verrazzano Bridge.

Instead, the state police plan to establish a "rolling block" that will slow traffic on each side of the new bridge to a crawl to clear the new bridge for the detonation. Afterward, there will be a quick inspection of the new bridge and then traffic will be allowed to pass. The delay is expected to last no more than 30 minutes, Corrao said.

The detonations will use 528 pounds of explosives on the two piers, which have been dismantled to just above the high-water line. The explosions, underwater, will create some splashes and ripples, but people lined up to drive across the new bridge, "won't see it, they won't even know it happened," Corrao said.

The Coast Guard will enforce a 3,000-foot safety zone on each side of the bridge. The demolition will not be canceled for poor weather unless there is a severe thunderstorm that could affect the electrical system used to control the detonations, Corrao said.

Once the smaller detonations are finished this fall, the only remaining portion of the old bridge will be a 2,000-foot stretch running from the North Kingstown shore. The DOT and the Department of Environmental Management are making plans to take that section down in a separate project.

June 12, 2006
7:06 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The next phase of demolition work on the old Jamestown Bridge begins this week, and this time, no explosives are involved.

The bridge's center span was taken down with explosives in April. Last month, the remaining spans and the top of the supporting piers were demolished, again with explosives.

The next phase is to take down the remaining concrete piers.

The Department of Transportation says crews will start work next week to use something called a hoe ram to break the piers apart.

The DOT says this mechanical demolition work will continue through August.

Once it's done, they'll use explosive charges to remove the portion of the piers that's below the water line.

May 18, 2006
8:34 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

Nice looking shot. Although there was a pretty good size section that looks like it got caught up and will have to be taken down manually. Other than that it looked great.

May 17, 2006
2:40 PM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

second phase of controlled demolition of the old Jamestown Bridge is planned for Thursday, and officials said the explosion will be bigger than the first.

Officials at the state Department of Transportation said contractors will set off almost 1,200 pounds of explosives sometime after 11:30 a.m. The demolition will be carried live online at http://www.turnto10.com

The explosions will sever 2,200 feet of deck trusses and girders on both sides of the bridge, which once connected North Kingstown to Jamestown. Demolition crews will also blow up the top 50 feet of two concrete piers that held up the center span, which was demolished last month.

May 12, 2006
10:21 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

The second phase of demolition on the old Jamestown Bridge has now been delayed until at least May 17.

Officials will keep an eye on the weather and decide over the weekend if a longer delay will be needed. The crews need a few consecutive days of dry weather to prepare for the project

May 3, 2006
8:47 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

[font=Verdana]The state plans to bring down two more sections on May 16th.

It will set explosives on sections of the two deck trusses that remain standing on either side of the gap.

At the same time, another set of explosives will destroy the tops of the central supporting
piers.

[/font]

April 19, 2006
8:26 PM
Avatar
Member
Forum Posts: 573
Member Since:
October 7, 2005
sp_UserOfflineSmall Offline

The superstructure blasts are always the most photogenic and usually get all the press but the real meat of the project which can make or break a contractor is the substructure especially the portion underwater. I can tell you some real horror stories. If you ever noticed, mediocre or incompetent marine contractors are virtually non existent. The potential for disaster is so great that one misstep can put you under.

April 19, 2006
7:19 PM
Avatar
Member
Forum Posts: 817
Member Since:
January 12, 2006
sp_UserOfflineSmall Offline

I came across a still shot in our local paper. No link though.

April 19, 2006
2:43 PM
Avatar
Member
Forum Posts: 573
Member Since:
October 7, 2005
sp_UserOfflineSmall Offline

Here are a lot of different angles of the shot if you are interested.

http://www.turnto10.com/news/8.....etail.html

April 18, 2006
1:33 PM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

Robert Kulinski said:
You have to give kudos to the Joseph B. Fay Company too.

My bad, I forgot. Sorry about that.

April 18, 2006
11:09 AM
Avatar
Wolf
Guest

The video is just awesome. Looks like a perfect shot! Congrats to all!

April 18, 2006
10:30 AM
Avatar
Member
Forum Posts: 573
Member Since:
October 7, 2005
sp_UserOfflineSmall Offline

You have to give kudos to the Joseph B. Fay Company too. They subbed out the demolition from Cashman. I've known them for about 20 years and they are one of the most competent companies in the business.

April 18, 2006
8:15 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

Congrats to Cashman and Demtech, looks like a nice shot. I heard it will take about 6 weeks to clean up the debris in the water.

April 17, 2006
10:57 AM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

Looks like the bridge is a go for tomorrow, April 18th

http://ww2.wpri.com/

Will carry a live streaming video

April 14, 2006
7:56 AM
Avatar
Member
Forum Posts: 573
Member Since:
October 7, 2005
sp_UserOfflineSmall Offline

Demtech is shooting it and they are being assisted by a local blasting contractor. Joseph B. Fay is subbing a large portion of the contract from Cashman.

http://www.thewesterlysun.com/...../news3.txt

April 7, 2006
2:24 PM
Avatar
Member
Forum Posts: 5298
Member Since:
August 29, 2005
sp_UserOfflineSmall Offline

Cashman Equipment of Boston has the demolition contact (20 million +/-)

I am not sure who is shooting it.

Here is a FAQ on the bridge demo: http://www.dot.state.ri.us/pro.....ochure.pdf

Forum Timezone: America/New_York

Most Users Ever Online: 429

Currently Online:
88 Guest(s)

Currently Browsing this Page:
2 Guest(s)

Top Posters:

James: 5298

demobud: 817

Robert Kulinski: 573

1Pyro: 548

autoparter: 534

Member Stats:

Guest Posters: 54

Members: 3042

Moderators: 0

Admins: 2

Forum Stats:

Groups: 4

Forums: 17

Topics: 20032

Posts: 28266

Administrators: JOHN: 7602, John: 7030

Skip to toolbar