[font=Verdana]Follow-up:[/font]
[font=Verdana]CityVest, the nonprofit developer at the helm of the Hotel Sterling renovation, announced Thursday it has selected Brandenburg Industrial Services Company for demolition at the site.[/font]
[font=Verdana]It could be weeks before buildings start coming down, and the demolition phase of the project should be complete by late summer, said Alex Rogers, executive director of CityVest.[/font]
[font=Verdana]Brandenburg[/font][font=Verdana], one of five firms that bid on the project, is based in [/font][font=Verdana]Chicago[/font][font=Verdana] but will oversee the Hotel Sterling project from its [/font][font=Verdana]Bethlehem[/font][font=Verdana] branch office, [/font][font=Verdana]Rogers[/font][font=Verdana] said.[/font]
[font=Verdana]The firm, which submitted a bid of just under $3 million, will begin environmental abatement work at the site immediately. Demolition work will follow but a detailed timeline is unavailable, [/font][font=Verdana]Rogers[/font][font=Verdana] said.[/font]
[font=Verdana]
[font=Verdana]Demolition professionals have indicated imploding the dilapidated 14-story Hotel [/font][font=Verdana]Sterling[/font][font=Verdana] tower could be the most cost-effective way to raze the structure, said Alex Rogers, executive director of CityVest.
"Buildings of this size in urban areas, (implosion) is what is typically done, but not always," [/font][font=Verdana]Rogers[/font][font=Verdana] said. "We're anxious to see what the bids say."
CityVest, a non-profit development corporation, is seeking professionals for environmental remediation and demolition at the [/font][font=Verdana]West Market Street[/font][font=Verdana] site. Interested firms must submit proposals by Jan. 11. Bids will reveal the project's cost.
Demolition and removing asbestos, lead-based paint and other environmental hazards should take two or three months to complete, weather permitting, [/font][font=Verdana]Rogers[/font][font=Verdana] said. CityVest believes some environmental and demolition work can be completed simultaneously.
"We want to get the work started," Rogers said. "There is plenty that can be done with or without snow on the ground. We're eager to move this project along."
Once the work is complete, it will allow CityVest to begin a full-scale revitalization of the hotel's main building - a seven-story structure at West Market and North River streets. Lower floors will house commercial businesses and top floors will be used for residential housing.
Beside the 14-story tower, a four-story building that connects the hotel buildings, and a two-story structure in the rear of the property that centralized its utilities, also will be razed.
The independent construction of each of the buildings clears some demolition obstacles, Rogers said. The goal will be to contain the work to the site as much as possible, he said.
"We don't want to inconvenience people who live and work downtown," Rogers said. "But at the same time we're going to make sure the activity occurs in a safe manner and nobody is placed in harm's way."
Renovation of the seven-story hotel and demolition work is expected to cost between $22 million and $24 million, Rogers said.
CityVest secured $9 million in government-related financing for the project. It has spent approximately $2 million on acquisition, design and restoration to date, Rogers said.
The non-profit organization will use the remaining $7 million and secure a loan to complete the project, Rogers said. Revenue generated from rent and other use of the building will cover the annual payments, he said.
Once the site is cleared, it will initially be used for parking for the revamped seven-story hotel, Rogers said. CityVest eventually wants to build another
residential/commercial building on the site[/font]
Most Users Ever Online: 429
Currently Online:
99 Guest(s)
Currently Browsing this Page:
1 Guest(s)
Member Stats:
Guest Posters: 54
Members: 3039
Moderators: 0
Admins: 2
Forum Stats:
Groups: 4
Forums: 17
Topics: 19932
Posts: 28166
Administrators: JOHN: 7602, John: 6930