Avatar

Please consider registering
guest

sp_LogInOut Log In sp_Registration Register

Register | Lost password?
Advanced Search

— Forum Scope —





 

— Match —





— Forum Options —





Minimum search word length is 3 characters - maximum search word length is 84 characters

sp_TopicIcon
3M Project
February 11, 2010
3:37 PM
Avatar
Member
Forum Posts: 160
Member Since:
April 4, 2008
sp_UserOfflineSmall Offline

Base Bid Alt 1 Alt 2 Alt 3
Rachel contracting $2,920,411 $235,251 $18,698 $3,276
Veit $3,430,728 $362,796 $31,216 $5,351
Bolander $3,439,200 $438,025 $33,700 $15,000
Landweher $3,474,280 $314,770 $11,300 $12,000
Homrich $3,704,441. $326,426 $80,000 $25,000
TC $3,836,400 $537,622 $20,000 $10,000
Cambria $3,931,459 $359,515 $35,000 $22,300
Frattalone $3,978,000 No bid No bid No Bid
Grant Mackay $4,272,884 $466,373 35,000 $35,000
Titan Wrecking $4,389,517 $451,390 10,500 No Bid
S&R Corp $4,534,184 $301,134 30100 34,000
Steininger $4,638,278 $380,457 6300 11500
Brandenburg $4,690,955 $520,552 29532 19140
Aherns $4,967,378 $369 10000 10000
Dore & Assoic $5,231,218 $388,075 19600 23200
CST $5,411,170 $597343 51750 28750
NASDI $5,594,497 $467,792 15000 19706
Sabre Demolition $5,962,567 $496,704 20,000 75000
Bierlien $6,337,825 $664,701 68725 67500

Base Bid was for Abatement, Demolition, and site restoration of Bldgs 41, 42, & 99 Complex, Alt 1 was Abatement, Demolition, Site Restoration of Bldg 2, Alt 2 was removing cooling unit of bldg 14 and alt 3 was painting bldg 1.

February 11, 2010
3:32 PM
Avatar
Member
Forum Posts: 198
Member Since:
December 29, 2005
sp_UserOfflineSmall Offline

$3.8 million sounds reasonable, but in today's crazy world, who knows???

February 11, 2010
1:45 PM
Avatar
Member
Forum Posts: 160
Member Since:
April 4, 2008
sp_UserOfflineSmall Offline

st paul mn

February 11, 2010
6:12 AM
Avatar
Member
Forum Posts: 9
Member Since:
November 20, 2009
sp_UserOfflineSmall Offline

Where ?

February 11, 2010
1:46 AM
Avatar
Member
Forum Posts: 160
Member Since:
April 4, 2008
sp_UserOfflineSmall Offline

That bids today. Any predictions on where the numbers will fall? Here is my guess for the 624,000 SF abatement, demolition, and site restoration.

Abatement for all buildings - 41 (25,000 sf), 42 (316,000 sf -8 stories), 99 complex (206,000 sf - made up of 10 -1 story steel manufacturing buildings) -Alt -1 Bldg 2 - 77,000 SF wood framed - 3 story - $1.3 -$1.6 million.

Above Grade Demolition - $800,000 (includes scrap steel & timber)
Below Grade Demolition - $300,000
Crushing - $150,000
Hotspot Remediation - $600,000 -$800,000
Site Restoration -(import of 52,000 cy, new sidewalks, street paving, etc) -$700,0000 -800,000
TOTAL - $3,850,000 -$4,450,000

Forum Timezone: America/New_York

Most Users Ever Online: 429

Currently Online:
70 Guest(s)

Currently Browsing this Page:
1 Guest(s)

Top Posters:

James: 5298

demobud: 817

Robert Kulinski: 573

1Pyro: 548

autoparter: 534

Member Stats:

Guest Posters: 54

Members: 3039

Moderators: 0

Admins: 2

Forum Stats:

Groups: 4

Forums: 17

Topics: 19932

Posts: 28166

Administrators: JOHN: 7602, John: 6930

Skip to toolbar